Decision Memo Completed

Martin Marietta Pipeline Project

Huron-Manistee National Forests Mason, Michigan Cadillac/Manistee Ranger District

Installation of a new brine pipeline. It is an addition to an existing permit for brine lines. The 12 inch diameter brine line would allow Martin Marietta to transport brine from production wells to the processing plant, and back to disposal wells.

Location

North side of Freeman Road, Grant Township, Mason County, Michigan

Project timeline

1
Scoping Start
11/08/2017
2
Decision
01/2018 (Estimated)
3
Implementation
01/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations