To provide electrical service to Consumers Energy customer. Installation of approximately 1,286 feet of underground electrical line, 34 feet west of centerline, 116th Ave, on National Forest land.
Location
W1/2, Section 31, T13N R16W, Otto Township, Oceana County, Michigan.
Project timeline
1
Scoping Start
01/05/2018
2
Decision
07/2018 (Estimated)
3
Implementation
07/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Consumers Energy Project Amendment #16 | Decision Signed Date: 07/19/2018 |
| Forests | Huron-Manistee National Forest |
| Districts | Baldwin/White Cloud Ranger District |
| Legal Land Description | Not Applicable |