Decision Memo Completed

Wolverine Power Substation Expansions

Huron-Manistee National Forests Lake, Michigan Baldwin/White Cloud Ranger District

Amending Wolverine Power's special use permit to authorize the expansion and rebuilding of two existing electrical substations. Rebuilds will respond to increased electric demand and improve reliability. Old equipment to be removed following rebuild.

Location

Lake County, T17N R12W, Section 19, and Lake County, T17N R13W, Section 3

Project timeline

1
Scoping Start
04/20/2018
2
Decision
08/2018 (Estimated)
3
Implementation
08/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Wolverine Power Substation ExpansionsDecision Signed Date: 08/06/2018
ForestsHuron-Manistee National Forest
DistrictsBaldwin/White Cloud Ranger District
Legal Land DescriptionLake County, T17N R12W, Section 19, and Lake County, T17N R13W, Section 3