Amending Wolverine Power's special use permit to authorize the expansion and rebuilding of two existing electrical substations. Rebuilds will respond to increased electric demand and improve reliability. Old equipment to be removed following rebuild.
Location
Lake County, T17N R12W, Section 19, and Lake County, T17N R13W, Section 3
Project timeline
1
Scoping Start
04/20/2018
2
Decision
08/2018 (Estimated)
3
Implementation
08/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Wolverine Power Substation Expansions | Decision Signed Date: 08/06/2018 |
| Forests | Huron-Manistee National Forest |
| Districts | Baldwin/White Cloud Ranger District |
| Legal Land Description | Lake County, T17N R12W, Section 19, and Lake County, T17N R13W, Section 3 |