Decision Memo Completed

Dry Lake Red Pine CE

Huron-Manistee National Forests Crawford, Michigan Mio Ranger District

The purpose of the project is to thin approximately 43 acres of red pine.

Location

The general location of this project is a red pine stand is located on the north side of Forest Service Road 3056 (Dry Lake Road) approximately 0.75 miles east of the intersection of Forest Service Road 3056 and State Highway M-18.

Project timeline

1
Scoping Start
11/15/2018
2
Decision
04/2019 (Estimated)
3
Implementation
04/2019 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (12), 36 Cfr 220.6(E)(12)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Timber Sales (Green)
Dry Lake Red Pine CEDecision Signed Date: 04/23/2019
ForestsHuron-Manistee National Forest
DistrictsMio Ranger District
Legal Land DescriptionT25N R1W, Section 27 in compartment 76
Forest productsFuels management