Decision Memo Completed

Consumers Energy Amendment #17

Huron-Manistee National Forests Lake, Michigan Baldwin/White Cloud Ranger District

To install an underground electrical line on National Forest land in the SE1/4 NE1/4 NE1/4, Section 20, T20N R11W, Dover Township, Lake County, Michigan. The proposal measures approximately 375 feet in length x 12 feet wide or .10 acres

Location

SE1/4 NE1/4 NE1/4, Section 20, T20N R11W, Dover Township, Lake County, Michigan.

Project timeline

1
Scoping Start
05/09/2019
2
Decision
06/2019 (Estimated)
3
Implementation
06/2019 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Consumers Energy Amendment #17Decision Signed Date: 06/19/2019
ForestsHuron-Manistee National Forest
DistrictsBaldwin/White Cloud Ranger District
Legal Land DescriptionNot Applicable
Special use management