This project will authorize an amendment to the GLEC 2019 special use permit for the maintenance of existing power lines and the installation of a new electric line.
Location
The general locations of this project include Wakeley Bridge Road, Goodar Road, and Ridge Road (Forest Service Road (FSR) 3043).
Project timeline
1
Scoping Start
08/06/2019
2
Decision
10/2019 (Estimated)
3
Implementation
01/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Great Lakes Energy Wakely Upgrades | Decision Signed Date: 10/09/2019 |
| Forests | Huron-Manistee National Forest |
| Districts | Mio Ranger District |
| Legal Land Description | Project 1) (Ridge Rd/ FSR 3043) T26N, R1E, S6 Project 2) (Wakeley Bridge Rd and Goodar Rd) T26N, R2W, S14 Project 3) (Goodar Rd) T26N, R2W, S13 |