This project will authorize the construction of 28.3 miles of non-motorized trail as part of the State's Iron Belle Trail System using volunteer and cooperative agreements. This project will also provide connectivity to existing USFS trail systems.
Location
The US Forest Service segment of the trail somewhat parallels River Road and part of M-65.
Project timeline
1
Scoping Start
09/30/2020
2
Comment Period
10/13/2021
3
Objection Period Start
01/05/2022
4
Decision
03/2022 (Estimated)
5
Implementation
03/2022 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Trail Management |
| Iosco Exploration Trail Project | Decision Signed Date: 03/07/2022 |
| Forests | Huron-Manistee National Forest |
| Districts | Huron Shores Ranger District |
| Legal Land Description | Not Applicable |