GLE will add new electric lines within their existing right of way on existing poles in 2 locations over 1,945 feet of line and in a 3rd location remove overhead lines and poles and bury the eclectic lines in that ROW for 4,450 feet.
Location
1)Blair Avenue and Lake Shore Drive in the Woodland Lake Subdivision, 2)near West Tower View Road and Little Manistee River Drive and 3) along Spruce Ave
Project timeline
1
Scoping Start
09/09/2021
2
Decision
11/2021 (Estimated)
3
Implementation
12/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Great Lake Energy Amendments 11 and 12 | Decision Signed Date: 11/08/2021 |
| Forests | Huron-Manistee National Forest |
| Districts | Baldwin/White Cloud Ranger District; Cadillac/Manistee Ranger District |
| Legal Land Description | T15N R13W Sections 9 and 10, Merrill Township, Newaygo County; T20N, R15W, Sections 19, 30, and 31, Michigan Meridian. Eden Township, Lake County, Michigan and; T13N R12W Section 27, Michigan Meridian. Everett Township, Newaygo County, Michigan |