To install fiber optic cables on GLECs existing overhead electric poles and/or adjacent to current buried electrical lines utilizing the existing electrical right-of-way.
Location
Newaygo and Oceana Counties, MI
Project timeline
1
Scoping Start
11/24/2021
2
Decision
01/2022 (Estimated)
3
Implementation
08/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| 2021 Great Lakes Energy Cooperative Fiber Optic Install | Decision Signed Date: 01/26/2022 |
| Forests | Huron-Manistee National Forest |
| Districts | Baldwin/White Cloud Ranger District |
| Legal Land Description | See scoping notice. |