Amend SU permit to add an o/h fiber optic line in T25N R19W Sect 16 & 21 (0.69 acres). Also amend permit to add O&M plan and to combine the two Forest permits for Sho-Me Tech LLC into one Forest permit MTF4032FO.
Location
New line will be installed in T25N R19W Sections 16 & 21
Project timeline
1
Scoping Start
06/28/2019
2
Decision
07/2019 (Estimated)
3
Implementation
07/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Sho-Me Technologies LLC SU Authorization MTF4032FO Amendment #1 | Decision Signed Date: 07/22/2019 |
| Forests | Mark Twain National Forest |
| Districts | Mark Twain National Forest All Units |
| Legal Land Description | Not Applicable |