Environmental Assessment Completed

Crane Lake High Hazard Dam Safety and Compliance

Mark Twain National Forest Iron, Missouri Potosi / Fredericktown Ranger District

Special project to address the safety and dam compliance concerns of the current structure.

Location

T32N R4E Sections 19, 28-33 - Iron County, MO

Project timeline

1
Scoping Start
09/26/2019
2
Comment Period
10/14/2020
3
Objection Period Start
03/17/2021
4
Decision
05/2021 (Estimated)
5
Implementation
10/2021 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFacility Improvements/Construction; Species Habitat Improvements; Heritage Resource Management; Watershed Improvements
Crane Lake High Hazard Dam Safety and ComplianceDecision Signed Date: 05/11/2021
ForestsMark Twain National Forest
DistrictsPotosi / Fredericktown Ranger District
Legal Land DescriptionT32N R4E Sections 19, 28-33 - Iron County, MO
Wildlife, fish, rare plantsWatershed managementFacility managementRecreation managementHeritage resource management