Replace the Laneville bridge. Construct short sections of new access roads and rehabilitate existing access roads.
Location
East of Laneville, at the beginning of FR 19, over Red Creek. Near the southwest border of the Dolly Sods Wilderness.
Project timeline
1
Scoping Start
01/04/2016
2
Decision
08/2016 (Estimated)
3
Implementation
11/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Decommissioning; Road Improvements/Construction |
| Laneville (Red Creek) Bridge Replacement | Decision Signed Date: 08/15/2016 |
| Forests | Monongahela National Forest |
| Districts | Potomac Ranger District |
| Legal Land Description | Not Applicable |