Reissue existing power lines, poles, and junction boxes on NFS lands to Mon Power. This will not authorize new construction.
Location
Throughout the Forest on various Districts. See land List and Map.
Project timeline
1
Scoping Start
03/31/2015
2
Decision
05/2015 (Estimated)
3
Implementation
05/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Monongahela Power Electrical Power Line Reissue Permit GBR205002 | Decision Signed Date: 05/13/2015 |
| Forests | Monongahela National Forest |
| Districts | Monongahela National Forest All Units |
| Legal Land Description | Not Applicable |