Amend Monongahela Power existing special use permit CHT205123 authorizing the relocation of an existing aerial 7.2 kV powerline to a buried powerline on National Forest System lands. This is needed to allow construction of Corridor H
Location
Randolph County / Montrose Quad / US Tract 16
Project timeline
1
Scoping Start
08/17/2017
2
Decision
09/2017 (Estimated)
3
Implementation
10/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Monongahela Power Montrose CHT205123 Amendment 2 | Decision Signed Date: 09/07/2017 |
| Forests | Monongahela National Forest |
| Districts | Cheat Ranger District |
| Legal Land Description | Randolph County / Montrose Quad / US Tract 16 |