This project proposes to upgrade the water system at Stuart Recreation Area Campground by installing 6" water main line to the meter location and 2" waterline to the campground to connect to the public water supply.
Location
The new pipeline will run from the center of Shavers Fork to the water meter and on to the Stuart Recreation Area Campground. The site is approximately 6 miles east of Elkins, WV.
Project timeline
1
Scoping Start
12/23/2019
2
Decision
03/2020 (Estimated)
3
Implementation
03/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Stuart Waterline Extension | Decision Signed Date: 03/16/2020 |
| Forests | Monongahela National Forest |
| Districts | Cheat Ranger District |
| Legal Land Description | Not Applicable |