WV Div of Highways & Federal Highways Admin seek new terms to replace expiring special use permits (SUP)s for temp construction activities & the construction, use, & maintenance of 2 roads associated with Corr H. This also includes a map correction.
Location
This project is located along the 4.9-mile section of Corridor H from Kerens to Parsons. The two roads are located approx. one mile and two miles west of the town of Moore, along US 219.
Project timeline
1
Scoping Start
11/24/2020
2
Decision
01/2021 (Estimated)
3
Implementation
01/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Corridor H - Kerens to Parsons Temporary Construction Activities/FLPMA Temporary Right-of-way SUPs | Decision Signed Date: 01/28/2021 |
| Forests | Monongahela National Forest |
| Districts | Cheat Ranger District |
| Legal Land Description | Not Applicable |