This project has been combined with the George Washington/Jefferson (GWJ) NF's "Zayo Fiber Optic Line Project #59879". The GWJ NF is the lead management unit. The combined project website is: www.fs.usda.gov/project/?project=5987
Location
Fiberoptic line would be installed along US Routes 219 and 32 & would cross into MNF land on Tracts 1403M, 113, 332-I, and 1403L, all located between Parsons and Thomas, WV.
Project timeline
1
Scoping Start
04/2021 (Estimated)
2
Decision
04/2021 (Estimated)
3
Implementation
04/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Monongahela National Forest |
| Districts | Cheat Ranger District |
| Legal Land Description | Not Applicable |