Columbia Gas Transmission LLC seeks a permit to install a cathodic protection system on existing pipeline to comply with safety regs. This would require 2 anode beds, 1.1 miles of power poles/line within their ex right of way, use of FR79 for access
Location
Proposed work would occur between the North Fork Mountain trail and Forest Road 79. Most work would occur within Columbia's ex right of way, except for the 2 anode beds (4 acres) outside of the ROW.
Project timeline
1
Scoping Start
07/2021 (Estimated)
2
Decision
08/2021 (Estimated)
3
Implementation
09/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Monongahela National Forest |
| Districts | Potomac Ranger District |
| Legal Land Description | Not Applicable |