Decision Memo Completed

FR1360 Improvement Project

Ottawa National Forest Houghton, Michigan Ottawa National Forest All Units

Improvement of road surface to address erosion and drainage issues resulting in rutting and sedimentation into adjacent wetlands and streams. Replace failing culverts. Includes replacing culvert at Boulder Creek to allow for aquatic organism passage.

Location

FR1360 is located on the Kenton and Ontonagon Districts, Houghton County, Michigan

Project timeline

1
Scoping Start
11/01/2016
2
Decision
01/2017 (Estimated)
3
Implementation
06/2017 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (18), 36 Cfr 220.6(E)(18)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
FR1360 Improvement ProjectDecision Signed Date: 01/24/2017
ForestsOttawa National Forest
DistrictsKenton Ranger District; Ontonagon Ranger District
Legal Land DescriptionNot Applicable
Road management