The project seeks to replace approximately 1,200ft of dock infrastructure in the Black River Harbor Recreation Area. The dock is requiring extensive maintenance and repair. This project also includes potential improvements to interpretative displays.
Location
T49N, R36W, Section 3
Project timeline
1
Scoping Start
05/13/2021
2
Decision
08/2021 (Estimated)
3
Implementation
04/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (19), 36 Cfr 220.6(E)(19); 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| Black River Harbor Dock Improvement II Project Decision Memo | Decision Signed Date: 08/19/2021 |
| Forests | Ottawa National Forest |
| Districts | Bessemer Ranger District |
| Legal Land Description | Not Applicable |