The project proposes the reconstruction, use and maintenance of existing Forest Roads, as well as construction of 3 short segments of non-system road, on order to access private property.
Location
Located on the east side of Perch Lake, east of Watersmeet, south of FR 4700.
Project timeline
1
Scoping Start
09/21/2021
2
Decision
06/2023 (Estimated)
3
Implementation
06/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Perch Lake Access | Decision Signed Date: 06/01/2023 |
| Forests | Ottawa National Forest |
| Districts | Watersmeet Ranger District |