This project proposes creating young forest through final harvest, improving diversity through intermediate harvest, restoring stand conditions through site preparation and prescribed burning and constructing temporary roads.
Location
The project is located about ten miles northwest of Grand Marais inTownships 61 and 62 North, Ranges 1 and 2 West
Project timeline
1
Scoping Start
06/25/2007
2
Comment Period
12/21/2007
3
Decision
03/2008 (Estimated)
4
Implementation
06/2008 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Species Population Enhancements; Road Improvements/Construction; Timber Sales (Salvage); Timber Sales (Green) |
| Cascade Project Decision Notice | Decision Signed Date: 03/21/2008 Legal Notice Date: 03/21/2008 |
| Forests | Superior National Forest |
| Districts | Gunflint Ranger District |