Access will mostly be on private land, in order to avoid a wet land the access will curve on FS lands for approximately 275 feet with a width of 25 feet.
Location
Location is in the Portage Lake area.
Project timeline
1
Scoping Start
01/02/2014
2
Decision
07/2014 (Estimated)
3
Implementation
08/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Special Use Access Requests | Decision Signed Date: 07/25/2014 Legal Notice Date: 07/25/2014 |
| Forests | Superior National Forest |
| Districts | Gunflint Ranger District |
| Legal Land Description | T64N, R2W, Section 3 by Portage Lake. |