Expansion of two gravel pits of less than 5 acres total. Gravel is needed for trail resurfacing and culvert installation.
Location
Gravel pits near August Lake, trail near FR387A
Project timeline
1
Scoping Start
10/24/2023
2
Decision
02/2024 (Estimated)
3
Implementation
06/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations; Trail Management |
| GAOA Gravel Pit Expansion | Decision Signed Date: 02/01/2024 |
| Forests | Superior National Forest |
| Districts | Kawishiwi Ranger District |
| Legal Land Description | August Lake Pit T61N, R10W, section 21 Kuusi Lake Pit T61N, R10W, section 23 |