Restoration of aquatic and riparian habitat in and adjacent to Oliverian Brook, including removal of fill previously dumped in side channel, removal of old bridge abutments, and rehabilitation of a portion of old Route 25.
Location
Oliverian Brook watershed, primarily in and adjacent to the opening at the base of Owl's Head Cliff in Benton, NH.
Project timeline
1
Scoping Start
04/11/2008
2
Decision
06/2010 (Estimated)
3
Implementation
07/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Oliverian Watershed Restoration Project | Decision Signed Date: 06/10/2010 |
| Forests | White Mountain National Forest |
| Districts | Pemigewasset Ranger District |