To eliminate ~1500' of wet trail, would relocate ~1000' to Forest Road 5049 and construct ~800' of connecting trail. Remaining 2.5 miles would be maintained (improved drainage, grading, brushing, widening) and minor realignments to accomodate groomer
Location
The project site is on the existing trail template for 2.5 miles, with 1,822 feet of trail relocation.
Project timeline
1
Scoping Start
02/10/2011
2
Decision
09/2011 (Estimated)
3
Implementation
09/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Bradley Brook Snowmobile Trail Relocation Decision Memo | Decision Signed Date: 09/22/2011 |
| Forests | White Mountain National Forest |
| Districts | Saco Ranger District |