A 1000 foot section of the Ellis River Trail is proposed for relocation due to a slump. Use of this section of the trail is prohibited as of April 1, 2011. A trail relocation is needed to bypass that location.
Location
Trail section to be relocated is approximately one mile north of the trail origin on Green Hill Road, in Jackson, NH.
Project timeline
1
Scoping Start
05/20/2011
2
Decision
07/2011 (Estimated)
3
Implementation
08/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Ellis River Nordic Trail Relocation Project Decision Memo | Decision Signed Date: 07/28/2011 |
| Forests | White Mountain National Forest |
| Districts | Saco Ranger District |