Issue a permit to Time Warner Cable Northeast LLC allowing them to extend fiber optic cable service to the existing wireless communication site on Mt. Tecumseh, including installing buried conduit under approx. 2,000%u2019 of ski trails.
Location
Within the Waterville Valley Ski Resort permit boundaries, Waterville, NH
Project timeline
1
Scoping Start
07/01/2014
2
Decision
07/2014 (Estimated)
3
Implementation
08/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Time Warner Waterville Valley Fiber Optic Cable Decision Memo | Decision Signed Date: 07/31/2014 |
| Forests | White Mountain National Forest |
| Districts | Pemigewasset Ranger District |
| Legal Land Description | Not Applicable |