Build a new 40-foot bridge to replace two 48-inch culverts that carry the flow of a tributary of the Sawyer river. An earthen section of the road would be excavated and bridge installed over the new void.
Location
Sawyer River Road about 1.5 miles from the gate off Route 302 in Hart's Location, New Hampshire
Project timeline
1
Scoping Start
12/30/2021
2
Decision
01/2023 (Estimated)
3
Implementation
04/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Road Improvements/Construction |
| Sawyer River Road Bridge Construction | Decision Signed Date: 01/31/2023 |
| Forests | White Mountain National Forest |
| Districts | Saco Ranger District |
| Legal Land Description | Not Applicable |