Decision Memo Completed

Eversource O154 T-Line Rebuild

White Mountain National Forest Coos, New Hampshire White Mountain National Forest All Units

Eversource proposes to rebuild the O154 115-kV transmission line within the existing right of way. The entire O154 line consists of 137 structures, 8 of which occur on Forest Service lands in the town of Stark, NH.

Location

About 3 acres of National Forest System lands in the Town of Stark, New Hampshire, just south of state highway 110.

Project timeline

1
Scoping Start
03/31/2022
2
Decision
10/2022 (Estimated)
3
Implementation
02/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Eversource O154 T-Line RebuildDecision Signed Date: 10/20/2022
ForestsWhite Mountain National Forest
DistrictsAndroscoggin Ranger District
Legal Land DescriptionNot Applicable
Special use management