Grafton County proposes to install about 9.5 miles of fiber optic line, about 7.2 miles aerially on existing utility poles and about 2.3 miles in new buried conduit.
Location
Project is in the towns of Landaff, Waterville Valley, Benton, Easton, and Orford, Grafton County, New Hampshire.
Project timeline
1
Scoping Start
09/30/2024
2
Decision
03/2025 (Estimated)
3
Implementation
05/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Grafton County Broadband Fiber Optic Installation Special Use Permit | Decision Signed Date: 03/05/2025 |
| Forests | White Mountain National Forest |
| Districts | Pemigewasset Ranger District |
| Legal Land Description | Not Applicable |