Approve a supplement to a mining plan of operations and new mining operations. Restore Resurrection Creek's channel, floodplain, and streamside vegetation to pre-mining conditions and enhance fish and riparian wildlife habitat.
Location
Seward Ranger District, Resurrection Creek
Project timeline
1
NOI in Federal Register
01/28/2008
2
DEIS NOA in Federal Register
07/23/2010
3
FEIS NOA in Federal Register
03/18/2015
4
Objection Period Start
03/25/2015
5
Decision
07/2015 (Estimated)
6
Implementation
07/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Ira - Inventoried Roadless Area Activities Requiring Secretary/Undersecretary Approval |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Species Habitat Improvements; Minerals Or Geology Plans Of Operations |
| Resurrection Creek Phase II:Stream Restoration & Hope Mining Co Plan of Ops | Decision Signed Date: 07/30/2015 |
| Forests | Chugach National Forest |
| Districts | Seward Ranger District |
| Legal Land Description | Not Applicable |