The U.S. Forest Service (USFS), Chugach National Forest is proposing to rebuild a 12-15 mile segment of the Quartz Creek 115kV transmission line
Location
The transmission line is located near Turnagain Pass between Ingram Creek and the Johnson Pass Trailhead, adjacent to approximately milepost 64 to milepost 75 of the Seward Highway
Project timeline
1
Scoping Start
12/06/2011
2
Decision
05/2012 (Estimated)
3
Implementation
06/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Forests | Chugach National Forest |
| Districts | Chugach National Forest All Units |
| Legal Land Description | T7N, R1E, Section 3;T8N, R1E, Sections 1, 12, 13, 14, 23, 26, 27, 34; T8N, R2E, Section 6; T9N, R2E, Sections 27, 28, 31, 32, 33 |