This project will relocate Section 2 of the existing Hope Distribution Feeder Electric line from M.P. 1.7 to M.P. 5.5 of the Hope Hwy.
Location
Hope Highway mile post 1.7 to mile post 5.5
Project timeline
1
Scoping Start
03/09/2012
2
Comment Period
03/06/2013
3
Decision
06/2013 (Estimated)
4
Implementation
09/2013 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Section 2 Relocation - Hope Powerline | Decision Signed Date: 06/07/2013 Legal Notice Date: 06/24/2013 |
| Forests | Chugach National Forest |
| Districts | Seward Ranger District |
| Legal Land Description | T8N, R1W, Seward Meridian, Alaska Section 3, T9N, R1W, Seward Meridian , Alaska, Sections 34, 27, & 22 |