The new alignment will require clearing a new 40-foot wide right-of-way along the west side of the Hope Highway and the installation of approximately 1500` of new overhead primary single-phase electric distribution line and retiring the existing line
Location
Mile post 5.5-5.8, Hope Highway
Project timeline
1
Scoping Start
09/26/2013
2
Comment Period
11/05/2013
3
Decision
02/2014 (Estimated)
4
Implementation
02/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Chugach Electric Association Section 3 Hope Feeder Electric Line Rebuild | Decision Signed Date: 02/06/2014 Legal Notice Date: 02/09/2014 |
| Forests | Chugach National Forest |
| Districts | Seward Ranger District |
| Legal Land Description | Section 22, T9N, R1W, Seward Meridian |