Stabilize the south bank and reshape the floodplain and channel of Primrose Creek prevent high water events from damaging roads and recreation facilities. Place boulders and anchor up to 60 whole trees along 500 feet of the south creek bank.
Location
Primrose Creek campground and Kenai Lake boat launch off the Primrose Spur road at the south end of Kenai Lake
Project timeline
1
Scoping Start
02/14/2014
2
Decision
04/2014 (Estimated)
3
Implementation
05/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (19), 36 Cfr 220.6(E)(19) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Primrose Creek Stabilization Decision Memo | Decision Signed Date: 04/04/2014 |
| Forests | Chugach National Forest |
| Districts | Seward Ranger District |
| Legal Land Description | T. 3 N, R.1 W, S. 24, Seward Meridian |