Renewal of an existing approved mining plan of operations
Location
Mills and Timberline Creeks near Summit Lake
Project timeline
1
Scoping Start
11/21/2014
2
Comment Period
11/22/2014
3
Decision
03/2015 (Estimated)
4
Implementation
04/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Timberline & Stormy Mining Plan of Operations | Decision Signed Date: 03/24/2015 |
| Forests | Chugach National Forest |
| Districts | Seward Ranger District |
| Legal Land Description | Township 7 North, Range 1 West, Section 35, Seward Meridian |