GCI is requesting to relocate 4,787' of existing underground fiber optic cable as part of Phase I Seward Highway MP 75-90 realignment at Portage Curve. And as part of Phase II, installation of 4,891' of cable & 5 access vaults.
Location
Along the Seward Highway MP81.5 - MP82 and MP84 - MP86
Project timeline
1
Scoping Start
10/06/2017
2
Decision
12/2017 (Estimated)
3
Implementation
03/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Nepa Document Prepared By Another Federal Agency |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| GCI Communication Corp Fiber Optic Facility Relocation | Decision Signed Date: 12/08/2017 |
| Forests | Chugach National Forest |
| Districts | Glacier Ranger District |
| Legal Land Description | Not Applicable |