To provide a safe multipurpose recreational path to connect facilities along a highly-recreated segment of the Seward Highway.
Location
Parallel to the Seward Highway near Portage, from the vicinity of MP 75 at Ingram Creek to MP 82 north of Twentymile River. Includes connections to recreation facilities outside the highway corridor.
Project timeline
1
Scoping Start
11/16/2017
2
Comment Period
08/27/2018
3
Objection Period Start
01/17/2019
4
Decision
03/2019 (Estimated)
5
Implementation
04/2019 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Dispersed Recreation Mgmt.; Trail Management |
| Portage Curve Multimodal Connector | Decision Signed Date: 03/12/2019 |
| Forests | Chugach National Forest |
| Districts | Glacier Ranger District |
| Legal Land Description | Not Applicable |