To allow construction an aerial tram and observation tower at Herring Bay under special use authorization, 5 miles south of Ketchikan. The tram would be constructed to the top of Fawn Mountain. CZMA FL/P-1
Location
A tram starting in Herring Bay and traveling to the top of Fawn Mountain
Project timeline
1
Scoping Start
10/01/2008
2
Comment Period
07/13/2010
3
Decision
12/2010 (Estimated)
4
Implementation
04/2011 (Estimated)
NEPA / regulatory detail
| Special Authority | Ira - Inventoried Roadless Area Activities Requiring Secretary/Undersecretary Approval |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Rain Forest Aerial Tram | Decision Signed Date: 12/14/2010 Legal Notice Date: 12/20/2010 |
| Forests | Tongass National Forest |
| Districts | Ketchikan Misty Fjords Ranger District |
| Legal Land Description | 55 ' 18" N, 131'34" W to 55'19"N, 131' 33" W |