Watershed restoration via in-stream work, road maintanence/decomissioning, and riparian thinning. Upland young growth thinning and gapping to improve understory forage production. Provide natural resource employment opportunities. FAA(4)
Location
Staney Creek watershed
Project timeline
1
Scoping Start
05/31/2008
2
Comment Period
04/23/2009
3
Decision
07/2009 (Estimated)
4
Implementation
07/2009 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Forest Vegetation Improvements; Species Habitat Improvements; Road Maintenance; Watershed Improvements |
| Staney Creek Enhancement & Restoration Project 1 | Decision Signed Date: 07/14/2009 Legal Notice Date: 07/18/2009 |
| Forests | Tongass National Forest |
| Districts | Thorne Bay Ranger District |