Address severe erosion issues currently existing by installing trail structures that will provide a hardened surface to accommodate the existing and future levels of visitor use.
Location
Etolin Island.
Project timeline
1
Scoping Start
04/12/2012
2
Decision
07/2012 (Estimated)
3
Implementation
05/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Burnett Inlet Portage Trail Construction | Decision Signed Date: 07/19/2012 |
| Forests | Tongass National Forest |
| Districts | Wrangell Ranger District |
| Legal Land Description | Trail extends between Forest Development Road (FDR) 51401 (Latitude, Longitude: 56.17202N, - 132.47956W, NAD 83) and the north shore of Burnett Inlet (Latitude, Longitude: 56.17026N, - 132.47266W, NA |