Complete physical and biological surveys on the Soule River watershed to investigate the feasibility of the Soule River Hydro Project FERC P-13528. Proponent is Soule Hydro, LLC. CZMA FL/P-2
Location
Soule River watershed, approximately nine miles southwest of Hyder, Alaska
Project timeline
1
Scoping Start
06/14/2010
2
Decision
09/2010 (Estimated)
3
Implementation
10/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Soule River Hydro Investigative Surveys | Decision Signed Date: 09/09/2010 |
| Forests | Tongass National Forest |
| Districts | Ketchikan Misty Fjords Ranger District |