Reconstruct approximately 500' of boardwalk trail replacing 14" boardwalk with 24" boardwalk and install 8 x 12 fiberglass grating boat pullout on the lakeshore.
Location
Wrangell Island. Highbush Lake Recreation Area
Project timeline
1
Scoping Start
05/01/2011
2
Decision
07/2011 (Estimated)
3
Implementation
09/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Highbush Lake Trail Reconstruction - Categorical Exclusion Letter to File | Decision Signed Date: 07/01/2011 |
| Forests | Tongass National Forest |
| Districts | Wrangell Ranger District |
| Legal Land Description | 56.19.49.04N; 132.05.11.76W |