This project is still being developed and will change because of new policy and direction. This project will include both young-growth and old-growth management and other non-timber resource activities. Project name will change.
Location
West side of Prince of Wales Island
Project timeline
1
NOI in Federal Register
04/2015 (Estimated)
2
DEIS NOA in Federal Register
05/2016 (Estimated)
3
FEIS NOA in Federal Register
09/2016 (Estimated)
4
Objection Period Start
10/2016 (Estimated)
5
Decision
12/2016 (Estimated)
6
Implementation
02/2017 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Forest Vegetation Improvements; Noxious Weed Treatments; Timber Sales (Green); Watershed Improvements |
| Forests | Tongass National Forest |
| Districts | Thorne Bay Ranger District |
| Legal Land Description | Not Applicable |