Approximately 70 acres of young growth harvest and approximately 1 mile of road construction in the Naukati area on Prince of Wales Island, to provide wood products, manage for future timber yield and enhance wildlife habitat.
Location
Thorne Bay Ranger District, Prince of Wales Island, Alaska
Project timeline
1
Scoping Start
04/23/2012
2
Comment Period
04/23/2012
3
Decision
02/2013 (Estimated)
4
Implementation
05/2013 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Forest Vegetation Improvements; Road Improvements/Construction; Timber Sales (Green) |
| Dargon Point Commerical Thinning Decision Notice and FONSI | Decision Signed Date: 02/19/2013 Legal Notice Date: 02/27/2013 |
| Forests | Tongass National Forest |
| Districts | Thorne Bay Ranger District |
| Legal Land Description | 55° 54" N, 133° 14' W – 3 miles NW of Naukati, Alaska |