Issue a special use permit to the FAA to install communications facilities at Kuiu Island. Facilities proposed include: 26' x 10' x 15' tall solar frame with solar panels; 6' x 8' x 17' tall equipment shelter; 20' x 20' helicopter landing pad.
Location
The Forest Service communications site is located on Kuiu Island.
Project timeline
1
Scoping Start
04/11/2013
2
Comment Period
04/11/2013
3
Decision
01/2014 (Estimated)
4
Implementation
03/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3); 32.2 (16), 36 Cfr 220.6(E)(16) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Plan Amendment |
| Communication Facility on Kuiu Island | Decision Signed Date: 01/15/2014 Legal Notice Date: 01/29/2014 |
| Forests | Tongass National Forest |
| Districts | Petersburg Ranger District |
| Legal Land Description | Not Applicable |