The 2013 Plan of Operations for surface exploration activities at the Salt Chuck Project proposes road-supported core diamond drilling at 25 sites.
Location
Township 72 South, Range 84 East, Sections 7 and 18
Project timeline
1
Scoping Start
06/26/2013
2
Comment Period
07/31/2013
3
Decision
09/2013 (Estimated)
4
Implementation
10/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Decision Memo Salt Chuck Project 2013 Plan of Operations | Decision Signed Date: 09/19/2013 Legal Notice Date: 09/21/2013 |
| Forests | Tongass National Forest |
| Districts | Thorne Bay Ranger District |
| Legal Land Description | Township 72 South, Range 84 East, Sections 7 and 18 |