Reissue an existing special use authorization to Thomas Reinarts for a 2.5 inch diameter x 300 foot long above ground water transmission line within the City of Kupreanof.
Location
Within the City of Kupreanof: 56 degrees 48.955 minutes 132 degrees 59.101 minutes (NAD 83).
Project timeline
1
Scoping Start
08/08/2013
2
Comment Period
08/08/2013
3
Decision
09/2013 (Estimated)
4
Implementation
01/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Reissue Water Transmission Line Special Use Permit | Decision Signed Date: 09/26/2013 Legal Notice Date: 11/07/2013 |
| Forests | Tongass National Forest |
| Districts | Petersburg Ranger District |
| Legal Land Description | Not Applicable |