Coeur Alaska requests authorization for Petro Marine to install a bulk fuel depot at the Kensington Mine to replace current iso-container fuel system.
Location
Berners Bay, Alaska; Kensington Slate Creek Cove Marine Facility; Upper Laydown Yard
Project timeline
1
Scoping Start
08/28/2014
2
Comment Period
06/26/2015
3
Objection Period Start
10/14/2015
4
Decision
01/2016 (Estimated)
5
Implementation
02/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction; Minerals Or Geology Plans Of Operations |
| 2014 Kensington Fuel Depot | Decision Signed Date: 01/22/2016 |
| Forests | Tongass National Forest |
| Districts | Juneau Ranger District |
| Legal Land Description | Not Applicable |